15.02.08 The Aas-Jakobsen/ViaNova network has been awarded the design contract for the double track tunnel section Oslo S - Ski (Follobanen). The design contract also covers possible open air sections between Oslo S and Vevelstad. The distance is approximatly 18 km. The work will be done in cooperation with Multiconsult, DNV and Spor architects.

The work is divided into the following phases:

  • Development of basis for main plan

  • Main plan

  • Detailed plan

  • Construction schedule / Tendor inquiring documents /

Construction drawings

  • Construction follow-up

The contract covers phase 1 "Review of basis for main plan" with option for the remaining phases.